Glass Installation Advances On City Of Miami Administration Building At Miami Freedom Park

Credit: Arquitectonica

Adler Development recently shared a construction update on LinkedIn showcasing the progress of curtain wall installation at the future City of Miami Administration Building, an 8-story, 124-foot-tall municipal office building at 1822 NW 37th Avenue within Miami Freedom Park. Designed by Arquitectonica, the complex will house municipal offices, City Commission chambers, and an adjoining multilevel parking garage. Moss Construction is the general contractor.

The aerial photos featured in the update show the majority of the office component enclosed in glass, much of which appears to retain its blue-green protective film. Installation has progressed around the rounded corners and undulating elevations of the reinforced concrete superstructure, with narrow horizontal bands tracing the perimeter of each floor plate. The alternating concave and convex curves along the longer elevations give the building a serpentine profile and accentuate its horizontal proportions. Portions of the exterior immediately beneath the roofline and along the ground floor and second floor remain exposed.

City of Miami Administration Building. Screenshot of a construction update shared by Adler Development on LinkedIn.

The eastern and western elevations curve inward toward the center of the building before widening toward its rounded ends, giving the office component the appearance of two elongated volumes connected by a narrower central section. A broad concrete canopy projects outward from the base of the elevation opposite the stadium, echoing the curvature of the floor plates above and sheltering a recessed ground-floor entrance.

The adjoining parking garage takes on a more rectilinear form with rounded corners and remains largely exposed. Formwork and steel reinforcement are visible across portions of the uppermost deck, and a red tower crane remains standing alongside the structure. Meanwhile, much of the office building’s roof is covered in a white roofing membrane, with mechanical equipment and several smaller rooftop enclosures situated within two large recessed sections.

Construction broke ground on January 15, 2025, and the office building topped out on July 10, 2026, nine days after the issuance of a $193 million construction permit.

Credit: Arquitectonica

Credit: Arquitectonica

According to Arquitectonica, the development will yield 748,975 square feet across a 2.1-acre site, comprising a 436,345-square-foot office component and a 312,630-square-foot, 11-story parking garage with capacity for 889 vehicles, including 179 EV-capable spaces. Arquitectonica is also responsible for the interior design, with ArquitectonicaGEO overseeing landscape architecture.

Credit: Arquitectonica

Credit: Arquitectonica

The new administrative headquarters will consolidate municipal operations currently housed at the Miami Riverside Center at 444 SW 2nd Avenue in Downtown Miami and City Hall at 3500 Pan American Drive in Coconut Grove. The facility will accommodate offices for the mayor and the five city commissioners, the city clerk’s office, and various municipal departments, including public works.

Credit: Arquitectonica

The property is located near Miami International Airport on the grounds of the former Melreese Golf Course, within the 130-acre Miami Freedom Park master plan, which encompasses Inter Miami CF’s Nu Stadium and a planned 58-acre public park.

Completion is anticipated in spring 2028.

Subscribe to YIMBY’s daily e-mail

Make YIMBY preferred on Google

Follow YIMBYgram for real-time photo updates
Like YIMBY on Facebook
Follow YIMBY’s Twitter for the latest in YIMBYnews

.

Be the first to comment on "Glass Installation Advances On City Of Miami Administration Building At Miami Freedom Park"

Leave a comment

Your email address will not be published.


*